Working Week 21-27 July 2007

Saturday 21st July Today work continued on the cooler group rebuild, the Gloucester lads were in attendance for the day and their first task was to adjust the left hand cooler group tank so that radiator elements fitted properly to both top and bottom rails. With this done, they then set about fitting one of the bottom tank coolant pipes and the bottom oil tank balance pipe. One of the lads continued the undercoating of No1 end nose compartment in readiness for gloss being applied. More cooler group water pipework was cleaned up and given a coat of primer. The opportunity was also taken this day to remove the covers between the power unit and main generator, this is so we could ascertain how the pair fit together in readiness for splitting them off later this year.

Sunday 22nd July Only a handful of members present today. More cooler group components were cleaned up and given the paint treatment today, these mainly being the fan drive shafts and the water pipes were given a coat of undercoat. With the undercoat now dry in No1 end nose compartment, the roof and walls were given a coat of grey gloss, it just needs the floor catching up now for this compartment to be ready for parts to be fitted back in.

Monday 23rd July Three of us were away from work for the next few days, so the opportunity for a mid week work session was taken. Today we managed to test the oil thermostat valve (or Ted valve as its now become! short for Teddington valve who manufactured it) This involved stripping the Ted down, the wax element was then placed in a pan (sorry Linda!) of hot water and heated up even more, this was to check the temperature it started to open and was fully open using a thermometer. It was then rebuilt and tested again, to ensure that the valve was moving ok and nothing stuck either shut or open. Once done, we headed off down to the coach to apply gloss to the water pipes and prep and prime the Ted valve.

Tuesday 24th July Three of us present again, we headed off down the coach and first job was to apply gloss to the Ted valve and fan drive shafts. We then set about fitting two pieces of conduit on the left hand side floor of the cooler group that had been missed previously, but in order to do this properly two long runs of conduit needed removing from the engine compartment, so out came the wire brushes, WD40 and brute force! Gaskets were made for the top water pipes and oil pipes ready for refitting.

A mega was borrowed from Castlecroft so we could get a general idea what condition the electrical left on D8233 were in after 20 years being stood. The results were surprising, the main generator and aux generator showed a good reading considering the amount of time they have been stood idle, the exciter's reading was even better, and the compressor motor's reading was as if it was brand new! The two exhausters reading were very low compared to the rest, but as all the motors on D8233 will be looked at and given a overhaul before use they shouldn't pose a problem. The top water pipes, were then refitted along with some of the top oil pipes in the cooler group then we all called it a day!

Wednesday 25th of July
Three became one today, as two of us had to return to the daily grind of home life and work! However Jason Lovell forged ahead with cooler group rebuild a short note of what he did is below:

Had a bit of a general tidy up in the support coach.
Then spent the rest of the day sorting out the sales stand stock and reboxing everything.

Thursday 26th July 2007 I made some additional gaskets for the Ted Valve and then fitted the valve to the base mounting pipe. Took the Ted valve assembly into the cooler group and fitted to the base plate on the floor & pipe flange to the bulkhead. I fitted the two outlet pipes to the valve, sealing the joints with the red gastight sealant. The Ermeto joints were then loosened to help locate the oil pipe flanges on the top radiator tanks. Once located, sealed & bolted down tight the L/H top oil pipe flange mounting. The R/H top oil pipe flange and then tightened all Ermeto joints as much as possible.

Friday 27th July 2007 Drelled radiator shutter air pipes they came out bright copper/brass finish, decided to fit unpainted. In the cooler group the shutter air pipes, bulkhead clamps were fitted and all joints tightened. Various cooler group components were located and prepared for fitting in the next working weekend. These included the large pipe clamp that fits the top of the oil bypass pipe, the fan drive couplings, filter drip tray drain pipe, fan brace bars and hanging brackets.

Over the seven days a lot was achieved, the cooler group is very nearly finished, the radiator fan itself is now away for repair and should be back at Bury in the not to distant future, everything left to rebuild in the
compartment is fan related (bar the elements) we are hoping that by September the cooler group will be done and we can move onto the engine compartment and No1 compartment.

Some photos of the work are below.

Above : Gareth Williams enjoys a cuppa while fitting the lower oil & water pipes. © C15PS
Above : Roy Chamberlain paints the grey undercoat in the nose end compartment. © C15PS
Above : Chris Tatton tightens up the oil pipe joints with a very big spanner. © C15PS
Above : The (Blue) "TED" valve is installed as is all the remaining oil pipework. © C15PS
Above : The thin air pipes for the radiator shutter cylinders has been cleaned & fitted. © C15PS

 

Fancy Getting Involved? click on the You Can Help page