We made some solid progress this month with Jason continuing the brake frame casing construction. Using new sheet steel and utilising the rollers put a curve into the side panel. Once that was done and tacked into place he made the top pieces and even cut out the holes for the train and loco brake controls.

Also this month, we took delivery of large quantity of cabling of differing thickness. This will be used throughout the loco, from the lighting circuits to powering the heavy stuff eg exhausters and compressor.

If you are interested in helping out please contact David Jenkins

 

Above : Sheet steel has been through the rollers and shaped accordingly. © C15PS
Above : Both units welded to the frames. © C15PS
Above : Taken delivery of the control cable. © C15PS
 

 

Fancy Getting Involved? click on the You Can Help page